TSPLOSTProjects

Project ID ROS- 18
Local ID NULL
Project Name Title Riverside Road Corridor Improvements
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City Roswell
Current Stage Construction
Project Description The Riverside Road Corridor Improvements will reconstruct the roadway corridor to include new sidewalks, bike lanes, and a multi-use trail between Riverside Park and Old Alabama Road near the GA-400 underpass and Don White Park.
Construction Firm Selected Backbone Infrastructure, LLC
Design Firm Selected Michael Baker Int'l
Estimated Design Completion Date June, 2024
Estimated Start Date For Project NULL
Estimated Construction Completion Date November, 2028
Estimated Substantial Completion Date NULL
Link To External Website https://www.roswellgov.com/government/departments/transportation/tsplost2
Primary Funding Source Sales Tax
TSPLOST Budget ($) $10,775,000
TSPLOST Dollars Spent ($) $1,751,937
TSPLOST Dollars Committed (not spent) ($) $9,023,063
Cost Status Green
Schedule Status Green
Status Active
Editor mdana@roswellgov.com
Project Year NULL
Last Update 2026-10-01 11:20:23
State Georgia
Address Riverside Road
Creation Date 2022-03-31