| Project ID | CSS- 5 |
| Local ID | TS107 |
| Project Name Title | SCOOT Upgrade |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Adaptive signal upgrade for 16 intersections. |
| Construction Firm Selected | RJ Haynie |
| Design Firm Selected | WSP |
| Estimated Design Completion Date | May, 2019 |
| Estimated Start Date For Project | July, 2018 |
| Estimated Construction Completion Date | June, 2021 |
| Estimated Substantial Completion Date | June, 2021 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,484,961 |
| TSPLOST Dollars Spent ($) | $1,484,961 |
| TSPLOST Dollars Committed (not spent) ($) | $0 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2021 |
| Last Update | 2022-07-29 17:51:46 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |