Project ID JCR- 31
Local ID TS0210
Project Name Title Old Alabama Bridge over Chattahoochee Tributary
Tier Tier 1
Project Type Bridges
Initiatve Type TSPLOST2
City Johns Creek
Current Stage Concept
Project Description Replace existing substandard bridge on Old Alabama Road over Chattahoochee Tributary just West of Autrey Mill Nature Preserve entrance.
Construction Firm Selected NULL
Design Firm Selected Michael Baker
Estimated Design Completion Date June, 2029
Estimated Start Date For Project October, 2029
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $3,250,000
TSPLOST Dollars Spent ($) $500,000
TSPLOST Dollars Committed (not spent) ($) $2,750,000
Cost Status Green
Schedule Status Green
Status Active
Editor brian.oconnor@johnscreekga.gov
Project Year 2026
Last Update 2026-08-17 16:22:32
State Georgia
Address City of Johns Creek
Creation Date 2022-03-31