TSPLOSTProjects

Project ID HA- 10
Local ID NULL
Project Name Title Sidewalk, Curb & Gutter Repairs
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City Hapeville
Current Stage Bidding
Project Description City wide replacement of dilapidated sidewalks on selected streets & N. Central Section Replacement
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date September, 2022
Estimated Start Date For Project November, 2025
Estimated Construction Completion Date April, 2026
Estimated Substantial Completion Date March, 2026
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,200,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $1,200,000
Cost Status Gray
Schedule Status Green
Status Active
Editor lsudduth@hapeville.org
Project Year NULL
Last Update 2025-09-22 12:17:26
State Georgia
Address City of Hapeville
Creation Date 2022-03-31