TSPLOSTProjects

Project ID HA- 9
Local ID NULL
Project Name Title I-85 Soundwall
Tier Tier 1
Project Type Roadway Projects
Initiatve Type TSPLOST2
City Hapeville
Current Stage Planning
Project Description Sound wall on I-85 corridor.
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date January, 2025
Estimated Start Date For Project May, 2025
Estimated Construction Completion Date December, 2025
Estimated Substantial Completion Date November, 2025
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $3,600,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $3,600,000
Cost Status Gray
Schedule Status Gray
Status Inactive
Editor lsudduth@hapeville.org
Project Year NULL
Last Update 2025-09-22 12:15:46
State Georgia
Address City of Hapeville
Creation Date 2022-03-31