TSPLOSTProjects

Project ID FA- 28
Local ID 23-002
Project Name Title SOUTHEAST BROAD STREET PEDESTRIAN IMPROVEMENTS PROJECT
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City Fairburn
Current Stage Completed
Project Description SOUTHEAST BROAD STREET PEDESTRIAN IMPROVEMENTS PROJECT #23-002. The work includes the removal of existing curb & gutter, sidewalk and driveway aprons as required, installation of new curb & gutter, installation of new sidewalk, replacement of existing sidewalk as required, installation of new driveway aprons, and the installation of new ADA handicap ramps. The contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt and concrete, as well as clean up and backfilling.
Construction Firm Selected The Corbet Group
Design Firm Selected Atlas Technical Consultants
Estimated Design Completion Date NULL
Estimated Start Date For Project NULL
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website Fairburn
Primary Funding Source Sales Tax
TSPLOST Budget ($) $678,277
TSPLOST Dollars Spent ($) $610,405
TSPLOST Dollars Committed (not spent) ($) $67,872
Cost Status Green
Schedule Status Green
Status Inactive
Editor anthony.belcher@fairburn.com
Project Year 2023
Last Update 2025-07-31 14:01:15
State Georgia
Address NULL
Creation Date 2022-03-31