TSPLOSTProjects

Project ID FA- 27
Local ID 25-004
Project Name Title City Wide Road Resurfacing
Tier Tier 1
Project Type Roadway Projects
Initiatve Type TSPLOST2
City Fairburn
Current Stage Construction
Project Description The City of Fairburn will accept sealed bids from qualified Contractors for furnishing all labor, equipment, and materials necessary to complete 4.1 mi of Roadway Improvements ON VARIOUS CITY ROADS Contract #25-004. The work includes milling, temporary traffic control, asphalt paving, manhole adjustments and associated tasks. The scope of Add Alternate #1 consists of the paving of the VETERANS OF FOREIGN WARS (VFW) parking lot located at 1699 Park Rd. Fairburn, GA 30213. All work must be completed within one hundred and twenty (120) calendar days of the Notice to Proceed (NTP).
Construction Firm Selected TRIPLE R CONSTRUCTION
Design Firm Selected In-house
Estimated Design Completion Date June, 2025
Estimated Start Date For Project July, 2025
Estimated Construction Completion Date November, 2025
Estimated Substantial Completion Date October, 2025
Link To External Website Fairburn
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,688,078
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $1,688,078
Cost Status Green
Schedule Status Green
Status Active
Editor anthony.belcher@fairburn.com
Project Year 2025
Last Update 2025-08-01 13:45:39
State Georgia
Address City of Fairburn
Creation Date 2022-03-31