| Project ID | CH- 11 |
| Local ID | NULL |
| Project Name Title | City Wide |
| Tier | Tier 2 |
| Project Type | Maintenance and Safety Enhancements |
| Initiatve Type | TSPLOST2 |
| City | Chattahoochee Hills |
| Current Stage | Construction |
| Project Description | traffic control, single pass chip seal, microsurfacing, thermoplastic solid traffic striping 5” white, thermoplastic solid traffic striping 5” yellow, thermoplastic traffic striping 24” white, thermoplastic skip traffic striping 5” white, and raised pavement markers single indicated on centerline for roadways identified by the engineers and public works director |
| Construction Firm Selected | Asphalt Paving Systems |
| Design Firm Selected | Keck & Wood |
| Estimated Design Completion Date | June, 2024 |
| Estimated Start Date For Project | April, 2024 |
| Estimated Construction Completion Date | June, 2024 |
| Estimated Substantial Completion Date | June, 2024 |
| Link To External Website | https://www.chatthillsga.us/ |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,213,788 |
| TSPLOST Dollars Spent ($) | $0 |
| TSPLOST Dollars Committed (not spent) ($) | $1,213,788 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | robbie.rokovitz@chatthillsga.us |
| Project Year | 2024 |
| Last Update | 2024-04-23 16:26:13 |
| State | Georgia |
| Address | City of Chattahoochee Hills |
| Creation Date | 2024-04-23 |