| Project ID | ALP- 71 |
| Local ID | C3004 |
| Project Name Title | Pedestrian Tunnel under Haynes Bridge Rd at GA 400 (Design Concept) |
| Tier | Tier 3 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST2 |
| City | Alpharetta |
| Current Stage | Design |
| Project Description | This project is for the construction of a pedestrian tunnel as part of the Alpha Loop trail system under Haynes Bridge Road to connect developments on the northern and southern sides of Haynes Bridge Road. Project is under design, managed by the North Fulton Community Improvement District (NFCID). |
| Construction Firm Selected | TBD |
| Design Firm Selected | TBD |
| Estimated Design Completion Date | Not Applicable |
| Estimated Start Date For Project | Not Applicable |
| Estimated Construction Completion Date | Not Applicable |
| Estimated Substantial Completion Date | Not Applicable |
| Link To External Website | https://cleargov.com/georgia/fulton/city/alpharetta/projects/3816/alpha-loop:-pedestrian-tunnel-under-haynes-bridge-rd-at-ga-400-(2022-parks-bond) |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $500,000 |
| TSPLOST Dollars Spent ($) | $0 |
| TSPLOST Dollars Committed (not spent) ($) | $500,000 |
| Cost Status | Gray |
| Schedule Status | Gray |
| Status | Active |
| Editor | kmcdowell@alpharetta.ga.us |
| Project Year | 2022 |
| Last Update | 2024-01-09 10:20:57 |
| State | Georgia |
| Address | Haynes Bridge Rd |
| Creation Date | 2022-03-31 |