TSPLOSTProjects

Project ID ALP- 65
Local ID C3002
Project Name Title Roundabout (Mayfield Rd at Canton St)
Tier Tier 3
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City Alpharetta
Current Stage Planning
Project Description This project is to perform necessary studies, evaluations, and analysis for replacement of the existing traffic signal at the intersection of Mayfield Road at Canton Street with a single-lane roundabout. Improved traffic flow and safety benefits are potential advantages of a roundabout compared to the existing traffic signal at this location. Since this project is a Tier 3 Project in the TSPLSOT Program, projects in Tier 1 are accomplished first prior to moving onto Tier 2 or 3 projects, unless there is a re-allocation of funds or revenue collected permits moving onto the other tiers.
Construction Firm Selected TBD
Design Firm Selected TBD
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project Not Applicable
Estimated Construction Completion Date Not Applicable
Estimated Substantial Completion Date Not Applicable
Link To External Website https://cleargov.com/georgia/fulton/city/alpharetta/projects/3811/roundabout:-mayfield-rd-at-canton-st-(tsplost_2,-tier_3)
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,000,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $2,000,000
Cost Status Gray
Schedule Status Gray
Status Active
Editor kmcdowell@alpharetta.ga.us
Project Year 2022
Last Update 2024-01-09 10:26:34
State Georgia
Address Mayfield Rd at Canton St
Creation Date 2022-03-31