TSPLOSTProjects

Project ID ALP- 62
Local ID C2230
Project Name Title Cumming St Corridor Improvements
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City Alpharetta
Current Stage Construction
Project Description The project consists of design and construction of pedestrian and bike safety improvements along Cumming Street, between Highway 9 and Westside Parkway. The proposed project would add a sidewalk on the south side of Cumming Street: 1) from Cricket Lane to Clairmonte Ave, and 2) from where the sidewalk stops on the east side of Henderson Pkwy to Westside Pkwy. Also, through this project, a dedicated right-turn lane will be provided from Westside Pkwy onto Cumming Street, and the sidewalk gap on Westside Pkwy (just south of Cumming Street) will be constructed.
Construction Firm Selected Sol Construction LLC
Design Firm Selected Moffatt & Nichol
Estimated Design Completion Date March, 2025
Estimated Start Date For Project July, 2022
Estimated Construction Completion Date September, 2026
Estimated Substantial Completion Date May, 2027
Link To External Website https://cleargov.com/georgia/fulton/city/alpharetta/projects/3806/cumming-st-corridor-improvements-(tsplost_2,-tier_1)
Primary Funding Source Sales Tax
TSPLOST Budget ($) $7,758,000
TSPLOST Dollars Spent ($) $6,001,940
TSPLOST Dollars Committed (not spent) ($) $1,756,060
Cost Status Green
Schedule Status Green
Status Active
Editor imisbach@alpharetta.ga.us
Project Year 2022
Last Update 2026-09-11 08:32:22
State Georgia
Address Cumming St
Creation Date 2022-03-31