Project ID ALP- 58
Local ID C2224
Project Name Title Raised intersection at Marietta St and Roswell St
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City Alpharetta
Current Stage Design
Project Description This is for safety improvements on Roswell Street between Old Roswell Street and Old Milton Pkwy. Some of the main elements included in this project are: wide sidewalk and pedestrian light poles on the east side of Roswell Street, and safety improvements at the intersection of Roswell Street and Marietta Street (4-way STOP controlled).
Construction Firm Selected TBD
Design Firm Selected Moffatt & Nichol
Estimated Design Completion Date January, 2024
Estimated Start Date For Project September, 2022
Estimated Construction Completion Date Not Applicable
Estimated Substantial Completion Date Not Applicable
Link To External Website https://cleargov.com/georgia/fulton/city/alpharetta/projects/3800/pedestrian-safety-improvements:-marietta-st-and-roswell-st-(tsplost_2,-tier_1)
Primary Funding Source Sales Tax
TSPLOST Budget ($) $350,000
TSPLOST Dollars Spent ($) $350,000
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status Green
Schedule Status Green
Status Active
Editor kmcdowell@alpharetta.ga.us
Project Year 2022
Last Update 2025-07-15 14:22:02
State Georgia
Address Marietta St
Creation Date 2022-03-31