Project Name Title Merk Road
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Planning
Project Description Multi-Use Trail Camp Creek Parkway to Aldredge Road
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date September, 2025
Estimated Start Date For Project September, 2025
Estimated Construction Completion Date June, 2026
Estimated Substantial Completion Date June, 2026
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,720,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $2,720,000
Cost Status NULL
Schedule Status NULL
Status Active