Project ID CSF- 296
Local ID OSI 629
Project Name Title Ono Rd/Hobgood Rd and Rivertown Rd
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Design
Project Description The 4-leg Stop controlled intersection was analyzed for traffic improvements and a roundabout alternative was selected. Additional improvements include 2.5-ft. curb & gutter, 2-ft. stamped concrete buffer, drainage, 5-ft. sidewalks, and streetlights. The proposed project will improve safety and relieve congestion.
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date December, 2027
Estimated Start Date For Project April, 2024
Estimated Construction Completion Date March, 2029
Estimated Substantial Completion Date March, 2029
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $258,060
TSPLOST Dollars Spent ($) $90,999
TSPLOST Dollars Committed (not spent) ($) $167,061
Cost Status NULL
Schedule Status NULL
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year 2024
Last Update 2026-09-22 09:45:38
State Georgia
Address Ono Rd/Hobgood Rd
Creation Date 2022-03-31