| Project ID | CSF- 296 |
| Local ID | OSI 629 |
| Project Name Title | Ono Rd/Hobgood Rd and Rivertown Rd |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST2 |
| City | City of South Fulton |
| Current Stage | Design |
| Project Description | The 4-leg Stop controlled intersection was analyzed for traffic improvements and a roundabout alternative was selected. Additional improvements include 2.5-ft. curb & gutter, 2-ft. stamped concrete buffer, drainage, 5-ft. sidewalks, and streetlights. The proposed project will improve safety and relieve congestion. |
| Construction Firm Selected | NULL |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | December, 2027 |
| Estimated Start Date For Project | April, 2024 |
| Estimated Construction Completion Date | March, 2029 |
| Estimated Substantial Completion Date | March, 2029 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $258,060 |
| TSPLOST Dollars Spent ($) | $90,999 |
| TSPLOST Dollars Committed (not spent) ($) | $167,061 |
| Cost Status | NULL |
| Schedule Status | NULL |
| Status | Active |
| Editor | roussan.francois@cityofsouthfultonga.gov |
| Project Year | 2024 |
| Last Update | 2026-09-22 09:45:38 |
| State | Georgia |
| Address | Ono Rd/Hobgood Rd |
| Creation Date | 2022-03-31 |