TSPLOSTProjects

Project ID CSF- 293
Local ID OSI 623
Project Name Title Butner Road and Aldredge Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Design
Project Description The T-intersection with a Stop control is being analyzed for traffic improvements including a roundabout alternative. Additional improvements include 2.5-ft. curb & gutter, 2-ft. stamped concrete buffer, drainage, 5-ft. sidewalks, and streetlights. The proposed project will improve safety and relieve congestion.
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date November, 2026
Estimated Start Date For Project April, 2024
Estimated Construction Completion Date January, 2029
Estimated Substantial Completion Date February, 2029
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $195,965
TSPLOST Dollars Spent ($) $28,400
TSPLOST Dollars Committed (not spent) ($) $167,565
Cost Status NULL
Schedule Status NULL
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year 2026
Last Update 2026-09-22 09:06:24
State Georgia
Address Butner Road
Creation Date 2022-03-31