TSPLOSTProjects

Project ID CSF- 288
Local ID T 271
Project Name Title Fairburn Rd
Tier Tier 1
Project Type Bridges
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Construction
Project Description The project is located on Fairburn Road, starting at Cascade Road and continuing to North Utoy Creek. The typical section includes 12' travel lanes, curb and gutter, a 10-foot multi-use path on the West side and a 6-foot wide sidewalk behind a 2-foot stamped concrete strip on the east side of Fairburn Road. Improvements also include bridge replacements at North and South Utoy Creek with bottomless culverts and turning lane improvements at the Fairburn Road/Cascade Road intersection.
Construction Firm Selected NULL
Design Firm Selected Qk4
Estimated Design Completion Date November, 2022
Estimated Start Date For Project March, 2023
Estimated Construction Completion Date December, 2026
Estimated Substantial Completion Date December, 2026
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,528,158
TSPLOST Dollars Spent ($) $2,506,248
TSPLOST Dollars Committed (not spent) ($) $21,910
Cost Status NULL
Schedule Status Yellow
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year 2023
Last Update 2026-09-17 09:34:06
State Georgia
Address Fairburn Rd
Creation Date 2022-03-31