TSPLOSTProjects

Project ID CSF- 287
Local ID B 508
Project Name Title Koweta Rd over Deep Creek
Tier Tier 1
Project Type Bridges
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Design
Project Description Bridge replacement to meet better rating capacity. The design consultant will evaluate the site survey and hydraulic study and size the proper culvert/bridge replacement. A complete street solution will be employed within the project limits
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date June, 2025
Estimated Start Date For Project June, 2026
Estimated Construction Completion Date November, 2028
Estimated Substantial Completion Date October, 2028
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $354,717
TSPLOST Dollars Spent ($) $31,613
TSPLOST Dollars Committed (not spent) ($) $323,104
Cost Status NULL
Schedule Status NULL
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year 2026
Last Update 2026-09-17 09:42:26
State Georgia
Address Koweta Rd
Creation Date 2022-03-31