TSPLOSTProjects

Project ID CSF- 284
Local ID RS 436
Project Name Title Woodside Hills
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Bidding
Project Description Deep base repair as needed, milling and resurface Woodside Drive Fern Valley Drive Fern Valley Court Green Hill Court Reynolds Road Red Berry Lane Zane Drive Faron Drive
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project April, 2024
Estimated Construction Completion Date August, 2024
Estimated Substantial Completion Date August, 2024
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $337,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $337,000
Cost Status NULL
Schedule Status NULL
Status Active
Editor jeff.mueller@cityofsouthfultonga.gov
Project Year 2024
Last Update 2023-02-28 21:59:44
State Georgia
Address Woodside Hills
Creation Date 2022-03-31