TSPLOSTProjects

Project ID CSF- 282
Local ID RS 435
Project Name Title Wolf Creek Country (Excluding Current Toppings)
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Bidding
Project Description Deep base repair as needed, milling and resurface Wolf Club Drive Wolf Club Court Wolf Lake Court Wolf Den Lane Wolf Trail Wolf Lake Drive Wolf View Court
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project April, 2025
Estimated Construction Completion Date August, 2025
Estimated Substantial Completion Date August, 2025
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $306,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $306,000
Cost Status NULL
Schedule Status NULL
Status Active
Editor jeff.mueller@cityofsouthfultonga.gov
Project Year 2025
Last Update 2023-02-28 21:57:39
State Georgia
Address Wolf Creek Country
Creation Date 2022-03-31