TSPLOSTProjects

Project ID CSF- 271
Local ID RS 346
Project Name Title Kimberly (units 3, 4a & 4b)
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Bidding
Project Description Deep base repair as needed, milling and resurface Adena Lane East and West Cainwood Drive Baxley Way Baxley Court West Forestside Court Forestside Court Cainwood Court East and West Woodburn Court Winkfield Place Winkfield Court Winkfield Point
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project August, 2023
Estimated Construction Completion Date November, 2023
Estimated Substantial Completion Date November, 2023
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $400,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $400,000
Cost Status NULL
Schedule Status NULL
Status Active
Editor jeff.mueller@cityofsouthfultonga.gov
Project Year 2023
Last Update 2023-02-28 21:16:11
State Georgia
Address Kimberly
Creation Date 2022-03-31