| Project ID | CSF- 271 |
| Local ID | RS 346 |
| Project Name Title | Kimberly (units 3, 4a & 4b) |
| Tier | Tier 1 |
| Project Type | Maintenance and Safety Enhancements |
| Initiatve Type | TSPLOST2 |
| City | City of South Fulton |
| Current Stage | Bidding |
| Project Description | Deep base repair as needed, milling and resurface Adena Lane East and West Cainwood Drive Baxley Way Baxley Court West Forestside Court Forestside Court Cainwood Court East and West Woodburn Court Winkfield Place Winkfield Court Winkfield Point |
| Construction Firm Selected | NULL |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | Not Applicable |
| Estimated Start Date For Project | August, 2023 |
| Estimated Construction Completion Date | November, 2023 |
| Estimated Substantial Completion Date | November, 2023 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $400,000 |
| TSPLOST Dollars Spent ($) | $0 |
| TSPLOST Dollars Committed (not spent) ($) | $400,000 |
| Cost Status | NULL |
| Schedule Status | NULL |
| Status | Active |
| Editor | jeff.mueller@cityofsouthfultonga.gov |
| Project Year | 2023 |
| Last Update | 2023-02-28 21:16:11 |
| State | Georgia |
| Address | Kimberly |
| Creation Date | 2022-03-31 |