TSPLOSTProjects

Project ID CSF- 263
Local ID RS 413
Project Name Title Creekside
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Bidding
Project Description Deep base repair as needed, milling and resurface Bigelow Court Stonecrop Drive Blazing Trail Creekside Cove Buckeye Place Chicory Cove Thistle Cove
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project April, 2025
Estimated Construction Completion Date August, 2025
Estimated Substantial Completion Date August, 2025
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $320,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $320,000
Cost Status NULL
Schedule Status NULL
Status Active
Editor jeff.mueller@cityofsouthfultonga.gov
Project Year 2025
Last Update 2023-03-02 19:12:07
State Georgia
Address Creekside
Creation Date 2022-03-31