| Project ID | CSF- 255 |
| Local ID | RST 219 |
| Project Name Title | Parkview Estates |
| Tier | Tier 1 |
| Project Type | Maintenance and Safety Enhancements |
| Initiatve Type | TSPLOST2 |
| City | City of South Fulton |
| Current Stage | Bidding |
| Project Description | Deep Base Repair, Topping Layer Added Rosehall Place Millberry Road Thornbud Road Trimrose Court Bigsage Drive |
| Construction Firm Selected | NULL |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | Not Applicable |
| Estimated Start Date For Project | August, 2023 |
| Estimated Construction Completion Date | November, 2023 |
| Estimated Substantial Completion Date | November, 2023 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $324,000 |
| TSPLOST Dollars Spent ($) | $0 |
| TSPLOST Dollars Committed (not spent) ($) | $324,000 |
| Cost Status | NULL |
| Schedule Status | NULL |
| Status | Active |
| Editor | jeff.mueller@cityofsouthfultonga.gov |
| Project Year | 2023 |
| Last Update | 2023-03-02 15:30:01 |
| State | Georgia |
| Address | Parkview Estates |
| Creation Date | 2022-03-31 |