TSPLOSTProjects

Project ID CSF- 218
Local ID RC 114
Project Name Title Bakers Ferry Rd SW
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Bidding
Project Description Deep base repair, milling, resurface and striping Boat Rock Road to Fulton Industrial Boulevard
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project August, 2023
Estimated Construction Completion Date November, 2023
Estimated Substantial Completion Date November, 2023
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $163,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $163,000
Cost Status NULL
Schedule Status NULL
Status Active
Editor jeff.mueller@cityofsouthfultonga.gov
Project Year 2023
Last Update 2023-02-27 21:35:17
State Georgia
Address Bakers Ferry Rd SW
Creation Date 2022-03-31