TSPLOSTProjects

Project ID CSF- 13
Local ID RS 370
Project Name Title Park Village
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Planning
Project Description Project not planned for resurfacing since it belongs to the city of Fairburn.
Construction Firm Selected NULL
Design Firm Selected Not Applicable
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project NULL
Estimated Construction Completion Date November, 2021
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $128,344
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $128,344
Cost Status Green
Schedule Status Green
Status Inactive
Editor roussan.francois@fultoncountyga.gov
Project Year NULL
Last Update 2023-03-02 14:20:38
State NULL
Address NULL
Creation Date NULL