| Project ID | Local ID | Project Name Title | Tier | Project Type | Initiatve Type | City | Current Stage | Project Description | Construction Firm Selected | Design Firm Selected | Estimated Design Completion Date | Estimated Start Date For Project | Estimated Construction Completion Date | Estimated Substantial Completion Date | Link To External Website | Primary Funding Source | TSPLOST Budget ($) | TSPLOST Dollars Spent ($) | TSPLOST Dollars Committed (not spent) ($) | Cost Status | Schedule Status | Status | Editor | Project Year | Last Update | State | Address | Creation Date |
| FA- 3 | 17-005 | Roadway Improvements on Various City Roads Project | Tier 1 | Maintenance and Safety Enhancements | TSPLOST | Fairburn | Completed | City-Wide Resurfacing. The project includes milling, temporary traffic control, asphalt paving, thermoplastic striping, manhole adjustments and associated tasks. Our strategy was to use 2017-2018 TSPLOST funds to focus our resurfacing efforts on the heart of the City (downtown) and extend future efforts to its extremities. In doing so, the implementation of the Downtown LCI Project, would have a more meaningful impact on the revitalization of FairburnÆs Historic Downtown. | E.R. Snell Contractor, Inc. | In-House | June, 2017 | November, 2017 | December, 2018 | October, 2018 | Sales Tax | $1,200,000 | $968,367 | $231,633 | Green | Green | Active | lthompson@fairburn.com | 2017 | NULL | NULL | NULL | NULL | |
| FA- 30 | 25-011 | Oakley Industrial Boulevard Left Turn Lane Project | Tier 3 | Congestion Relief | TSPLOST2 | Fairburn | Construction | The project consists of a total of 0.299 miles of widening to install a left turn lane along Oakley Industrial Boulevard at entrance of the SC Johnson's Distribution Center. The budget impact will be $1,315,247.57. Of which, $1,065,807.57 will be reimbursed by the South Fulton Community Improvement District (CID) through an Intergovernmental Agreement (IGA). Thereby reducing the overall TSPLOST budget impact to $249,440. The Notice to Proceed (NTP) with Construction was September 29th, 2025. The project is currently behind schedule due to significant utility conflicts and inclement weather. • City of Fairburn Power relocations and switchover complete as of April 16, 2026. • Comcast completed their utility relocation work that conflicted with the project proposed grading. • Time extension of 150 calendar days approved on 2/17/2026 due to delays with utility conflicts. • 20 days from 7/22/2026 – 8/19/2026 lost due to rain / wet conditions and utility relocations. • AT&T continuing utility relocation work. Bores have been done, but the handholes have not been set due to awaiting splicing. Section cuts and out-of-service cuts are currently being arranged. This work was originally scheduled to be completed 8/7, but now fiber splicing is scheduled to be completed by 8/21. Once splicing has completed, handholes will be reset. • Plans for the following month consist of Piedmont Paving finishing water main installation, side drain installation, and grading for roadway extension. This work is dependent upon AT&T completing their utility work | Piedmont Paving, Inc. | Atlas Technical Consultants | July, 2025 | September, 2025 | January, 2026 | December, 2025 | Fairburn | Sales Tax | $1,315,248 | $60,531 | $1,254,717 | Green | Red | Active | lthompson@fairburn.com | 2025 | 2026-09-02 11:55:47 | Georgia | Oakley Industrial Boulevard | 2022-03-31 |
| FA- 31 | 24-009 | McLarin Road/E. Broad Street (Bohannon Road to Gullat Road) Full-Depth Reclamation | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Completed | Full-Depth Reclamation of McLarin Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. From Bohannon Rd. to Gullatt Road. | BLOUNT CONSTRUCTION | SOUTHEASTERN ENGINEERING INC. | NULL | NULL | NULL | NULL | Sales Tax | $100,000 | $100,000 | $0 | Green | NULL | Active | lthompson@fairburn.com | 2024 | 2026-08-31 11:56:48 | Georgia | McLarin Road | 2022-03-31 | |
| FA- 32 | 24-009 | Gullatt Road Full-Depth Reclamation | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Completed | "Full-Depth Reclamation of Gullatt Road from McLarin Road East to just west of Cleckler Road. The project also included asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. The approved T-SPLOST Project List allocates $$674,612.00 of Roadway Projects funding to the Full-Depth Reclamation of Gullatt Road. Total Project cost 2,658,412.08 | BLOUNT CONSTRUCTION | SOUTHEASTERN ENGINEERING INC. | April, 2024 | July, 2024 | November, 2024 | October, 2024 | Sales Tax | $337,306 | $674,612 | $-337,306 | Green | Green | Active | anthony.belcher@fairburn.com | 2024 | 2025-08-04 16:36:16 | Georgia | Gullatt Road | 2022-03-31 | |
| FA- 33 | NULL | Quiet Zone R/R Crossings | Tier 2 | Operation and Safety Improvements | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 34 | 23-002 | Pedestrian and Bike Improvements (Phase 2) | Tier 2 | Pedestrian and Bike Improvements | TSPLOST2 | Fairburn | Completed | SOUTHEAST BROAD STREET PEDESTRIAN IMPROVEMENTS PROJECT #23-002. The work includes the removal of existing curb & gutter, sidewalk and driveway aprons as required, installation of new curb & gutter, installation of new sidewalk, replacement of existing sidewalk as required, installation of new driveway aprons, and the installation of new ADA handicap ramps. The contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt and concrete, as well as clean up and backfilling. | The Corbet Group | Moreland Altobelli | November, 2022 | January, 2023 | May, 2023 | April, 2023 | Sales Tax | $678,277 | $678,277 | $0 | Green | Green | Inactive | anthony.belcher@fairburn.com | 2023 | 2025-07-02 16:33:59 | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 35 | NULL | City Wide | Tier 3 | Congestion Relief | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 36 | NULL | City Wide | Tier 3 | Operation and Safety Improvements | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 37 | NULL | Dodd Street Roundabout | Tier 3 | Operation and Safety Improvements | TSPLOST2 | Fairburn | Planning | Project removed from consideration. | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | $0 | $0 | $0 | NULL | NULL | Inactive | lthompson@fairburn.com | NULL | 2026-08-31 10:46:31 | Georgia | Dodd Street | 2022-03-31 | |
| FA- 38 | NULL | Pedestrian and Bike Improvements (Phase 3) | Tier 3 | Pedestrian and Bike Improvements | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 39 | NULL | Oakley Industrial Boulevard Extension (Design Only) | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Design | The extension of Oakley Industrial Boulevard, from Creekwood Road to Gullatt Road. The project design is approximately 90% complete. The South Fulton Community Improvement District (CID) is covering the project's design costs. The City of Fairburn expended approximately $15,823 in TSPLOST Funds on a Task Order with Atlas Technical Consultants for roadway staking and subsurface exploration to investigate the soil conditions for excavation purposes at the proposed Oakley Industrial Boulevard Extension between stations 104+00, 105+00, 108+00, 109+00, 110+00, and 111+00. The project is currently in the ROW Acquisition Phase. There is a total of nine (9) parcels, with five (5) parcels remaining. This phase is holding up the project due to a stalemate in negotiations, making it significantly behind schedule. The most recent rough construction cost estimate is $4,950,000.00 as of 1/22/2026. | NULL | SOUTHEASTERN ENGINEERING INC. | March, 2027 | October, 2027 | December, 2028 | October, 2028 | Sales Tax | $0 | $15,823 | $-15,823 | Green | Red | Active | lthompson@fairburn.com | NULL | 2026-08-31 11:46:25 | Georgia | Oakley Industrial Boulevard | 2022-03-31 | |
| FA- 4 | 17-004 | Pedestrian Improvements on Various City Roads Project | Tier 1 | Pedestrian and Bike Improvements | TSPLOST | Fairburn | Completed | The project includes grading complete, temporary traffic control, installation of sidewalk, driveway reconstruction, installation of handicap ramps, curb & gutter installation, header curb installation and associated tasks. The is the first TSPLOST Pedestrian and Bike Improvements Project. The objective was to install new sidewalk and handicap ramps at various locations throughout the City that were currently not served with pedestrian facilities. The project also proposed connection to existing pedestrian facilities in the area. The project's purpose was to improve safety by providing a safe means for pedestrian to walk downtown to access various services and amenities. The project also provided pedestrians a safe means by which access to the newly renovated Clarence Duncan Memorial Park. | TOPLE Construction & Engineering | In-House | July, 2017 | November, 2017 | November, 2018 | November, 2018 | Sales Tax | $439,288 | $193,565 | $245,723 | Green | Green | Active | lthompson@fairburn.com | 2017 | NULL | NULL | NULL | NULL | |
| FA- 40 | 25-003 | MULLIS STREET PEDESTRIAN IMPROVEMENTS PROJECT | Tier 1 | Pedestrian and Bike Improvements | TSPLOST2 | Fairburn | Construction | The installation of a 5-foot concrete sidewalk with a 2-foot beauty strip along Mullis Street, from West Campbellton Street to Dodd Street, and from Dodd Street to Strickland Street. The project also entails the installation of pedestrian improvements on a section of Dodd Street, from Mullis Street to W. Broad Street. The work includes the removal of existing curb & gutter and header curb, and the installation of new header curb and sidewalk. This contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt as well as clean up and backfilling. The scope of Add Alternate #1 consists of the installation of pedestrian lighting | CONSTRUCTION 57 INC. | POND ENGINEERING | March, 2025 | May, 2025 | July, 2025 | June, 2025 | Sales Tax | $570,201 | $570,201 | $0 | Green | Green | Active | anthony.belcher@fairburn.com | 2025 | 2025-05-06 10:21:42 | GA | NULL | 2025-05-06 | |
| FA- 41 | 24-009 | Cleckler Rd Full-Depth Reclamation Project | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | Fairburn | Completed | Full-Depth Reclamation of Cleckler Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. The total project costs were $445,687.77. The South Fulton CID covered first $209,041.09 in construction costs, the remaining $236,646.68 in construction costs was paid for with TSPLOST Funds. | BLOUNT CONSTRUCTION | SOUTHEASTERN ENGINEERING INC. | May, 2024 | July, 2024 | November, 2024 | October, 2024 | Sales Tax | $209,041 | $239,647 | $-30,606 | Green | Green | Active | lthompson@fairburn.com | 2024 | 2026-08-31 11:55:35 | GA | Cleckler Rd. | 2025-05-06 | |
| FA- 42 | 25-011 | Oakley Industrial Boulevard Left Turn Lane Project | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Bidding | This project consists of a total of 0.299 miles of Widening on Oakley Industrial Boulevard at the entrance of SC Johnson's distribution center. | PIEDMONT PAVING | Atlas Technical Consultants | May, 2025 | July, 2025 | November, 2025 | October, 2025 | Fairburn | Sales Tax | $330,000 | $0 | $330,000 | Gray | Gray | Active | anthony.belcher@fairburn.com | 2025 | 2025-08-01 14:37:15 | Georgia | 314 NW Broad St | 2025-06-16 |
| FA- 43 | NULL | BROOKS DRIVE EXTENSION ROADWAY PROJECT | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Design | Brooks Drive Extension Roadway Project is to extend Brooks Drive from Fisher Street to the dead end, west of the New Beginning Senior Center. The design also includes the widening and reconstruction of Brooks Drive, from Washington Street to the dead end. The Task Order for $272,400 with Atlas Technical Consultants to Design the Brooks Drive Extension Roadway Project was approved at the March 25th, 2024, City Council Meeting. The project is currently in the Right-of-Way (ROW) Acquisition Phase. As of August 24th, 2026, an agreement has been reached on 14 of the 22 parcels. To date $272,372.23 has been spent on design services; $131,334.69 has been spend on ROW acquisition services; and $87,224.00 spent on the required ROW and easements or approximately $490,930.92. | NULL | Atlas Technical Consultants | April, 2027 | NULL | NULL | NULL | Sales Tax | $1,500,000 | $490,931 | $1,009,069 | Green | Green | Active | lthompson@fairburn.com | 2025 | 2026-08-26 15:52:52 | NULL | NULL | 2025-07-31 | |
| FA- 44 | 23-003 | Rivertown Connector Project | Tier 1 | Roadway Projects | TSPLOST | Fairburn | Planning | City of Fairburn Roadway Project design to provide connectivity between Rivertown Road and Virlyn B. Smith Road. | NULL | SOUTHEASTERN ENGINEERING INC. | April, 2025 | May, 2025 | August, 2025 | July, 2025 | Sales Tax | $937,240 | $0 | $937,240 | Gray | Gray | Inactive | anthony.belcher@fairburn.com | 2020 | 2025-05-01 11:30:19 | NULL | NULL | NULL | |
| FA- 45 | NULL | White Mill Road Full-Depth Reclamation | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | Fairburn | Completed | The Full-Depth Reclamation of White Mill Road from SR 92 (Campbellton-Fairburn Road) to Rivertown Road, which is mostly with the City of South Fulton and partially inside the City of Fairburn. Through an IGA the City of South Fulton covered $1,270,558.31, and the City of Fairburn covered 158,400. | Atlanta Paving & Concrete Construction, Inc. | NULL | NULL | January, 2023 | June, 2023 | NULL | Sales Tax | $816,700 | $158,400 | $658,300 | Green | Green | Active | lthompson@fairburn.com | 2023 | 2026-08-31 11:57:27 | NULL | NULL | NULL | |
| FA- 46 | 26-004 | Roadway Improvements on Various City Roads | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | Fairburn | Construction | The Project was put out to bid April 22, 2026. The Bid Opening date was May 22, 2026 The Contract Award to Shepco Paving, Inc. for the Roadway Improvements on Various City Roads Project for the bid amount of $2,008,660.20 was approved by Mayor & Council at the June 8, 2026, City Council Meeting. The Notice of Award was issued to Shepco Paving, Inc. on June 10th, 2026. The Notice to Proceed (NTP) with Construction Date was July 13th, 2026. In this year's City-Wide Resurfacing Project approximately ten (10) centerline miles of roadway, which includes eight (8) residential subdivisions will be resurfaced. The City of Fairburn will combine Grant Funding and TSPLOST Funding to deliver this project to take advantage of the economies of scale. In doing so, the first $253,421.47 in project expenditures will be covered by an LMIG Grant from the Georgia Department of Transportation (GDOT); and the second $276,464.46 in project expenditures will be covered by a Local Road Assistance Grant from GDOT, for a total of $529,885.93 collectively to be covered by grants. The remaining project expenditures ($1,478,774.27) will be covered by TSPLOST Funds. | Shepco Paving, Inc | In-House | March, 2026 | July, 2026 | July, 2026 | December, 2026 | Fairburn | Sales Tax | $2,008,660 | $0 | $2,008,660 | Green | Green | Active | lthompson@fairburn.com | 2026 | 2026-09-02 12:58:12 | GA | City of Fairburn | 2022-03-31 |
| FA- 47 | 26-005 | Harris Road Full-Depth Reclamation | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | Fairburn | Construction | Prior to putting the project out to bid, the City of Fairburn requested funding assistance from the South Fulton CID to help deliver the Harris Road Full-Depth Reclamation Project. The CID agreed to pay $300,000 toward the construction of the project, with the understanding that Green Oil would cover the balance of the funding required to complete the construction. The agreement was subsequently formalized through an approves Intergovernmental Agreement (IGA). Through an approved Memorandum of Understanding (MOU), Green Oil agreed to reimburse and provide upfront funding for the Project Advertisement, Preliminary Engineering and Design Services, Construction Management, Project Management, and the Construction Engineering and Inspection (CEI) Services costs associated with the Project for a total of $107,925 in total project funding. The Invitation for Bid (IFB) for the Harris Road Full-Depth Reclamation Project was advertised on April 22nd, 2026. The bid opening date was May 22nd, 2026. The bid of the lowest responsive and responsible bidder came in at $369,725.75. Mayor and Council approved the Contract Award to Blount Construction Company, Inc. for the Harris Road Full-Depth Reclamation Project for the bid amount of $369,725.75 at the July 13th, 2026, City Council Meeting. The project entails full depth reclamation, asphalt paving and striping on Harris Road, from just west of Shortleaf Road (the Fairburn Family Travel Center Truck Stop exit) to the Senoia Road (SR74) Right-of-Way Limits. All work must be completed within sixty (60) calendar days of the Notice to Proceed with Construction (NTP). The first ($300,000) in project expenditures will come out of account number (360-0000-54-1421) T-SPLOST Fund, SFCID – Harris Road FDR. The remaining project expenditures ($69,725.75) will come out of account number (360-0000-52-1410) TSPLOST Fund, Infrastructure - Roadway. | Blount Construction Company, Inc. | Atlas Technical Consultants | March, 2026 | September, 2026 | October, 2026 | October, 2026 | Fairburn | Sales Tax | $369,726 | $0 | $369,726 | Green | NULL | Active | lthompson@fairburn.com | 2026 | 2026-09-02 13:00:04 | GA | City of Fairburn | 2026-09-01 |
| SUM = 34,759,772 | SUM = 17,310,181 | SUM = 17,449,591 |