| Project ID | Local ID | Project Name Title | Tier | Project Type | Initiatve Type | City | Current Stage | Project Description | Construction Firm Selected | Design Firm Selected | Estimated Design Completion Date | Estimated Start Date For Project | Estimated Construction Completion Date | Estimated Substantial Completion Date | Link To External Website | Primary Funding Source | TSPLOST Budget ($) | TSPLOST Dollars Spent ($) | TSPLOST Dollars Committed (not spent) ($) | Cost Status | Schedule Status | Status | Editor | Project Year | Last Update | State | Address | Creation Date |
| FA- 3 | 17-005 | Roadway Improvements on Various City Roads Project | Tier 1 | Maintenance and Safety Enhancements | TSPLOST | Fairburn | Completed | City-Wide Resurfacing. The project includes milling, temporary traffic control, asphalt paving, thermoplastic striping, manhole adjustments and associated tasks. Our strategy was to use 2017-2018 TSPLOST funds to focus our resurfacing efforts on the heart of the City (downtown) and extend future efforts to its extremities. In doing so, the implementation of the Downtown LCI Project, would have a more meaningful impact on the revitalization of FairburnÆs Historic Downtown. | E.R. Snell Contractor, Inc. | In-House | June, 2017 | November, 2017 | December, 2018 | October, 2018 | Sales Tax | $1,200,000 | $968,367 | $231,633 | Green | Green | Active | lthompson@fairburn.com | 2017 | NULL | NULL | NULL | NULL | |
| FA- 30 | 25-011 | Oakley Industrial Boulevard Left Turn Lane Project | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Bidding | The widening of 0.299 mi of a left turn lane for Oakley Industrial Boulevard at entrance of the SC Johnson's distribution enter. | PIEDMONT PAVING | Atlas Technical Consultants | July, 2025 | August, 2025 | January, 2026 | December, 2025 | Fairburn | Sales Tax | $1,315,248 | $0 | $1,315,248 | Green | Green | Active | anthony.belcher@fairburn.com | 2025 | 2025-08-01 14:35:20 | Georgia | Oakley Industrial Boulevard | 2022-03-31 |
| FA- 31 | 24-009 | McLarin Road/E. Broad Street (Bohannon Road to Gullat Road) Full-Depth Reclamation | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Completed | Full-Depth Reclamation of McLarin Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. From Bohannon Rd. to Gullatt Road. | BLOUNT CONSTRUCTION | SOUTHEASTERN ENGINEERING INC. | NULL | NULL | NULL | NULL | Sales Tax | $100,000 | $100,000 | $0 | Green | NULL | Active | lthompson@fairburn.com | 2024 | 2025-06-24 11:13:11 | Georgia | McLarin Road | 2022-03-31 | |
| FA- 32 | 24-009 | Gullatt Road Full-Depth Reclamation | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Completed | "Full-Depth Reclamation of Gullatt Road from McLarin Road East to just west of Cleckler Road. The project also included asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. The approved T-SPLOST Project List allocates $$674,612.00 of Roadway Projects funding to the Full-Depth Reclamation of Gullatt Road. Total Project cost 2,658,412.08 | BLOUNT CONSTRUCTION | SOUTHEASTERN ENGINEERING INC. | April, 2024 | July, 2024 | November, 2024 | October, 2024 | Sales Tax | $337,306 | $674,612 | $-337,306 | Green | Green | Active | anthony.belcher@fairburn.com | 2024 | 2025-08-04 16:36:16 | Georgia | Gullatt Road | 2022-03-31 | |
| FA- 33 | NULL | Quiet Zone R/R Crossings | Tier 2 | Operation and Safety Improvements | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 34 | 23-002 | Pedestrian and Bike Improvements (Phase 2) | Tier 2 | Pedestrian and Bike Improvements | TSPLOST2 | Fairburn | Completed | SOUTHEAST BROAD STREET PEDESTRIAN IMPROVEMENTS PROJECT #23-002. The work includes the removal of existing curb & gutter, sidewalk and driveway aprons as required, installation of new curb & gutter, installation of new sidewalk, replacement of existing sidewalk as required, installation of new driveway aprons, and the installation of new ADA handicap ramps. The contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt and concrete, as well as clean up and backfilling. | The Corbet Group | Moreland Altobelli | November, 2022 | January, 2023 | May, 2023 | April, 2023 | Sales Tax | $678,277 | $678,277 | $0 | Green | Green | Inactive | anthony.belcher@fairburn.com | 2023 | 2025-07-02 16:33:59 | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 35 | NULL | City Wide | Tier 3 | Congestion Relief | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 36 | NULL | City Wide | Tier 3 | Operation and Safety Improvements | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 37 | NULL | Dodd Street Roundabout | Tier 3 | Roadway Project | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | Dodd Street | 2022-03-31 | |
| FA- 38 | NULL | Pedestrian and Bike Improvements (Phase 3) | Tier 3 | Pedestrian and Bike Improvements | TSPLOST2 | Fairburn | Planning | NULL | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | NULL | NULL | $0 | NULL | NULL | Active | NULL | NULL | NULL | Georgia | City of Fairburn | 2022-03-31 | |
| FA- 39 | NULL | Oakley Industrial Boulevard Extension (Design Only) | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Concept | The extension of Oakley Industrial Boulevard, from Creekwood Road to Gullatt Road. | NULL | NULL | June, 2025 | August, 2025 | November, 2025 | October, 2025 | Sales Tax | $0 | $0 | $0 | Green | Green | Active | anthony.belcher@fairburn.com | NULL | 2025-08-01 14:57:15 | Georgia | Oakley Industrial Boulevard | 2022-03-31 | |
| FA- 4 | 17-004 | Pedestrian Improvements on Various City Roads Project | Tier 1 | Pedestrian and Bike Improvements | TSPLOST | Fairburn | Completed | The project includes grading complete, temporary traffic control, installation of sidewalk, driveway reconstruction, installation of handicap ramps, curb & gutter installation, header curb installation and associated tasks. The is the first TSPLOST Pedestrian and Bike Improvements Project. The objective was to install new sidewalk and handicap ramps at various locations throughout the City that were currently not served with pedestrian facilities. The project also proposed connection to existing pedestrian facilities in the area. The project's purpose was to improve safety by providing a safe means for pedestrian to walk downtown to access various services and amenities. The project also provided pedestrians a safe means by which access to the newly renovated Clarence Duncan Memorial Park. | TOPLE Construction & Engineering | In-House | July, 2017 | November, 2017 | November, 2018 | November, 2018 | Sales Tax | $439,288 | $193,565 | $245,723 | Green | Green | Active | lthompson@fairburn.com | 2017 | NULL | NULL | NULL | NULL | |
| FA- 40 | 25-003 | MULLIS STREET PEDESTRIAN IMPROVEMENTS PROJECT | Tier 1 | Pedestrian and Bike Improvements | TSPLOST2 | Fairburn | Construction | The installation of a 5-foot concrete sidewalk with a 2-foot beauty strip along Mullis Street, from West Campbellton Street to Dodd Street, and from Dodd Street to Strickland Street. The project also entails the installation of pedestrian improvements on a section of Dodd Street, from Mullis Street to W. Broad Street. The work includes the removal of existing curb & gutter and header curb, and the installation of new header curb and sidewalk. This contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt as well as clean up and backfilling. The scope of Add Alternate #1 consists of the installation of pedestrian lighting | CONSTRUCTION 57 INC. | POND ENGINEERING | March, 2025 | May, 2025 | July, 2025 | June, 2025 | Sales Tax | $570,201 | $570,201 | $0 | Green | Green | Active | anthony.belcher@fairburn.com | 2025 | 2025-05-06 10:21:42 | GA | NULL | 2025-05-06 | |
| FA- 41 | 24-009 | Cleckler Rd Full-Depth Reclamation Project | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | Fairburn | Bidding | Full-Depth Reclamation of Cleckler Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. | BLOUNT CONSTRUCTION | SOUTHEASTERN ENGINEERING INC. | May, 2024 | July, 2024 | November, 2024 | October, 2024 | Sales Tax | $209,041 | $0 | $209,041 | Green | Green | Active | anthony.belcher@fairburn.com | 2024 | 2025-08-04 16:18:35 | GA | Cleckler Rd. | 2025-05-06 | |
| FA- 42 | 25-011 | Oakley Industrial Boulevard Left Turn Lane Project | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Bidding | This project consists of a total of 0.299 miles of Widening on Oakley Industrial Boulevard at the entrance of SC Johnson's distribution center. | PIEDMONT PAVING | Atlas Technical Consultants | May, 2025 | July, 2025 | November, 2025 | October, 2025 | Fairburn | Sales Tax | $330,000 | $0 | $330,000 | Gray | Gray | Active | anthony.belcher@fairburn.com | 2025 | 2025-08-01 14:37:15 | Georgia | 314 NW Broad St | 2025-06-16 |
| FA- 43 | NULL | BROOKS DR. EXTENSION | Tier 1 | Roadway Projects | TSPLOST2 | Fairburn | Design | Extension of 0.2 mi of Brooks Dr. | NULL | NULL | January, 2024 | NULL | NULL | NULL | Sales Tax | $100,000 | $0 | $100,000 | Green | NULL | Active | anthony.belcher@fairburn.com | 2025 | 2025-08-03 19:06:57 | NULL | NULL | 2025-07-31 | |
| FA- 5 | 18-002 | Oakley Industrial Boulevard Full-Depth Reclamation (FDR) Project | Tier 1 | Roadway Projects | TSPLOST | Fairburn | Completed | Full-Depth Reclamation of Oakley Industrial Boulevard, from Bohannon Road to just west of SR 74/ Senoia Road. The project also included asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. The approved T-SPLOST Project List allocates $897,309 of Roadway Projects funding to the Full-Depth Reclamation of Oakley Industrial Boulevard (OIB). Since we only did approximately half of the entire project, only $448,654.50 of TSPLOST Funds were allocated to the project.. | C.W.Matthews Contracting Co., Inc. | Moreland Altobelli Associates, LLC | May, 2018 | July, 2018 | February, 2019 | January, 2019 | Sales Tax | $629,879 | $411,049 | $218,830 | Green | Green | Active | lthompson@fairburn.com | 2018 | 2021-09-08 19:22:03 | NULL | NULL | NULL | |
| FA- 6 | 18-002 | McLarin Road Full-Depth Reclamation Project | Tier 1 | Maintenance and Safety Enhancements | TSPLOST | Fairburn | Completed | Full-Depth Reclamation of McLarin Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. | C.W.Matthews Contracting Co., Inc. | Moreland Altobelli Associates, LLC | May, 2018 | July, 2018 | February, 2019 | January, 2019 | Sales Tax | $524,177 | $330,790 | $193,387 | Green | Green | Active | lthompson@fairburn.com | 2018 | NULL | NULL | NULL | NULL | |
| FA- 7 | 18-002 | Terminus Drive Full-Depth Reclamation Project | Tier 1 | Maintenance and Safety Enhancements | TSPLOST | Fairburn | Completed | Full-Depth Reclamation of Terminus Drive along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and the adjustment of manholes and water valves. | C.W.Matthews Contracting Co., Inc. | Moreland Altobelli Associates, LLC | May, 2018 | July, 2018 | February, 2019 | January, 2019 | Sales Tax | $622,226 | $341,612 | $280,614 | Green | Green | Active | lthompson@fairburn.com | 2018 | NULL | NULL | NULL | NULL | |
| FA- 8 | 18-006 | Roadway Improvements on Various City Roads Project | Tier 1 | Maintenance and Safety Enhancements | TSPLOST | Fairburn | Completed | City-Wide Resurfacing. The project includes milling, temporary traffic control, asphalt paving, thermoplastic striping, manhole adjustments and associated tasks. City-Wide Resurfacing. This yearÆs project we again focused our resurfacing efforts on the heart of the City (downtown) in preparation for the implementation of Downtown LCI Project and extend future efforts to its extremities. In addition to areas in close proximity to downtown, this yearÆs project list also contains other priorities and cooperative efforts identified by Staff. The Invitation for Bid (IFB#18-006, Roadway Improvements on Various City Roads) was advertised on May 16th. The bid opening was bid opening date was June 15th, 2018 at 3:00 pm at which time the four (4) bids were opened and read aloud. After completion of the bid evaluation, it was determined that Baldwin Paving Company, Inc. was the lowest responsive and responsible bidder with a bid price of $2,289,810.12. | Baving Paving, Inc. | In-House | July, 2018 | October, 2018 | October, 2019 | April, 2019 | Sales Tax | $2,165,861 | $1,717,810 | $448,051 | Green | Yellow | Active | lthompson@fairburn.com | 2018 | 2020-12-17 13:26:23 | NULL | NULL | NULL | |
| SUM = 27,539,367 | SUM = 13,803,843 | SUM = 13,735,524 |