| Project ID | Local ID | Project Name Title | Tier | Project Type | Initiatve Type | City | Current Stage | Project Description | Construction Firm Selected | Design Firm Selected | Estimated Design Completion Date | Estimated Start Date For Project | Estimated Construction Completion Date | Estimated Substantial Completion Date | Link To External Website | Primary Funding Source | TSPLOST Budget ($) | TSPLOST Dollars Spent ($) | TSPLOST Dollars Committed (not spent) ($) | Cost Status | Schedule Status | Status | Editor | Project Year | Last Update | State | Address | Creation Date |
| CSF- 28 | RS 384 | Robinson Woods Drive | Tier 1 | Maintenance and Safety Enhancements | TSPLOST | City of South Fulton | Completed | The roads (Old Bethsaida Way and Robinson Wood Drive) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled. | NULL | Not Applicable | Not Applicable | NULL | November, 2020 | NULL | Sales Tax | $68,961 | $92,695 | $-23,734 | Red | Green | Active | roussan.francois@fultoncountyga.gov | 2019 | 2021-05-03 20:17:33 | NULL | NULL | NULL | |
| CSF- 280 | RS 431 | Retreat at Jones Mill | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | City of South Fulton | Bidding | Deep base repair as needed, milling and resurface Shamrock Drive | NULL | NULL | Not Applicable | April, 2024 | August, 2024 | August, 2024 | Sales Tax | $116,000 | $0 | $116,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2024 | 2023-02-28 21:42:40 | Georgia | Retreat at Jones Mill | 2022-03-31 | |
| CSF- 281 | RS 433 | Three Lakes | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | City of South Fulton | Bidding | Deep base repair as needed, milling and resurface Three Lakes Drive Twin Lakes Drive Meadow Lake Road | NULL | NULL | Not Applicable | April, 2025 | August, 2025 | August, 2025 | Sales Tax | $114,000 | $0 | $114,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2025 | 2023-02-28 21:53:39 | Georgia | Three Lakes | 2022-03-31 | |
| CSF- 282 | RS 435 | Wolf Creek Country (Excluding Current Toppings) | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | City of South Fulton | Bidding | Deep base repair as needed, milling and resurface Wolf Club Drive Wolf Club Court Wolf Lake Court Wolf Den Lane Wolf Trail Wolf Lake Drive Wolf View Court | NULL | NULL | Not Applicable | April, 2025 | August, 2025 | August, 2025 | Sales Tax | $306,000 | $0 | $306,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2025 | 2023-02-28 21:57:39 | Georgia | Wolf Creek Country | 2022-03-31 | |
| CSF- 283 | T 276 | Cochran Road over Deep Creek | Tier 1 | Bridges | TSPLOST2 | City of South Fulton | Land | The proposed project will replace the bridge carrying Cochran Road over Deep Creek. The project begins 280 ft. south of the existing bridge and ends 280 ft. north of the existing bridge. This project would replace the existing substandard bridge over Deep Creek with a new structure and new roadway approaches. The proposed mainline will consist of two 11Æ-0ö travel lane and curb and gutter in each direction. Sidewalks will be constructed in each direction for the full project length. A 2.0Æ buffer will be provided between the sidewalk and curb. | NULL | Long Engineering | December, 2022 | March, 2023 | February, 2024 | NULL | Sales Tax | $1,530,000 | $160,000 | $1,370,000 | NULL | Yellow | Active | jeff.mueller@cityofsouthfultonga.gov | 2023 | 2023-03-02 20:49:31 | Georgia | Cochran Road | 2022-03-31 | |
| CSF- 284 | RS 436 | Woodside Hills | Tier 1 | Maintenance and Safety Enhancements | TSPLOST2 | City of South Fulton | Bidding | Deep base repair as needed, milling and resurface Woodside Drive Fern Valley Drive Fern Valley Court Green Hill Court Reynolds Road Red Berry Lane Zane Drive Faron Drive | NULL | NULL | Not Applicable | April, 2024 | August, 2024 | August, 2024 | Sales Tax | $337,000 | $0 | $337,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2024 | 2023-02-28 21:59:44 | Georgia | Woodside Hills | 2022-03-31 | |
| CSF- 285 | B 505 | Derrick Rd over Deep Creek Tributary | Tier 1 | Bridges | TSPLOST2 | City of South Fulton | Planning | Bridge replacement to meet better rating capacity and alleviate congestion | NULL | NULL | March, 2025 | June, 2025 | March, 2026 | March, 2026 | Sales Tax | $2,280,000 | $0 | $2,280,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2025 | 2023-03-02 20:52:16 | Georgia | Derrick Rd | 2022-03-31 | |
| CSF- 286 | T 270 | Demooney Road over Deep Creek | Tier 1 | Bridges | TSPLOST2 | City of South Fulton | Land | The project begins 1,000' southwest of the existing bridge and ends 980' northeast of the existing bridge. It will replace the existing substandard bridge with a new structure and new roadway approaches. The proposed typical section consists of 12' travel lanes with curb and gutter along with sidewalks in each direction within the project limits. | NULL | Long Engineering | April, 2023 | July, 2023 | December, 2024 | December, 2024 | Sales Tax | $3,090,000 | $260,000 | $2,830,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2023 | 2023-03-02 20:48:47 | Georgia | Demooney Road | 2022-03-31 | |
| CSF- 287 | B 508 | Koweta Rd over Deep Creek | Tier 1 | Bridges | TSPLOST2 | City of South Fulton | Planning | Bridge replacement to meet better rating capacity | NULL | NULL | June, 2025 | June, 2026 | March, 2027 | March, 2027 | Sales Tax | $2,227,000 | $0 | $2,227,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2026 | 2023-03-02 21:00:49 | Georgia | Koweta Rd | 2022-03-31 | |
| CSF- 288 | T 271 | Fairburn Rd | Tier 1 | Bridges | TSPLOST2 | City of South Fulton | Bidding | The project is located on Fairburn Road, starting at Cascade Road and continuing to North Utoy Creek. The typical section includes 12' travel lanes, curb and gutter, a 10-foot multi-use path on the West side and a 6-foot wide sidewalk behind a 2-foot stamped concrete strip on the east side of Fairburn Road. Improvements also include bridge replacements at North and South Utoy Creek with bottomless culverts and turning lane improvements at the Fairburn Road/Cascade Road intersection. | NULL | Qk4 | November, 2022 | March, 2023 | September, 2024 | September, 2024 | Sales Tax | $3,372,000 | $37,000 | $3,335,000 | NULL | Yellow | Active | jeff.mueller@cityofsouthfultonga.gov | 2023 | 2023-03-02 20:58:17 | Georgia | Fairburn Rd | 2022-03-31 | |
| CSF- 289 | B 503 / T 288 | Stacks Rd over CSX RR | Tier 1 | Bridges | TSPLOST2 | City of South Fulton | Design | This project consists of replacement of bridge structure on Stacks Road over the CSX Railroad. | NULL | American Engineers, Inc. | December, 2023 | June, 2024 | December, 2024 | December, 2024 | Sales Tax | $2,712,000 | $48,000 | $2,664,000 | NULL | Green | Active | jeff.mueller@cityofsouthfultonga.gov | 2024 | 2023-03-02 21:04:01 | Georgia | Stacks Rd | 2022-03-31 | |
| CSF- 29 | RS 385 | Sable Chase S/D | Tier 1 | Maintenance and Safety Enhancements | TSPLOST | City of South Fulton | Completed | The roads (Carriage Chase Road, Devon Chase Road, Sable Chase Lane, Sable Glen Lane, Sable Glen Road, Sable Run Road, and Sable View Lane) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled. | NULL | Not Applicable | Not Applicable | NULL | July, 2021 | NULL | Sales Tax | $480,812 | $326,570 | $154,242 | Green | Green | Active | roussan.francois@fultoncountyga.gov | 2020 | 2021-10-12 18:33:56 | NULL | NULL | NULL | |
| CSF- 290 | OSI 620 | Aldredge Road and Merk Road | Tier 1 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | Intersection improvements will include the addition of a circular roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage, curb & gutter, streetlights, and 5' wide sidewalks. | NULL | NULL | November, 2025 | November, 2025 | March, 2027 | March, 2027 | Sales Tax | $1,550,000 | $0 | $1,550,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2025 | 2023-03-02 19:22:10 | Georgia | Aldredge Road | 2022-03-31 | |
| CSF- 291 | OSI 622 | Bethlehem Rd and Cedar Grove Rd | Tier 1 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | The intersection is being analyzed for traffic improvements including a roundabout alternative. Additional improvements include curb & gutter, drainage, sidewalks, and streetlights. The proposed project will improve safety and relieve congestion. | NULL | NULL | September, 2026 | September, 2026 | December, 2027 | December, 2027 | Sales Tax | $1,110,000 | $0 | $1,110,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2026 | 2023-03-02 19:26:37 | Georgia | Bethlehem Rd | 2022-03-31 | |
| CSF- 292 | OSI 600 | Bethsaida Road and Creel / West Road | Tier 1 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | The intersection is being analyzed for traffic improvements including a roundabout alternative. Additional improvements include curb & gutter, drainage, sidewalks, and streetlights. The proposed project will improve safety and relieve congestion. | NULL | NULL | June, 2025 | September, 2025 | March, 2027 | March, 2027 | Sales Tax | $1,835,000 | $0 | $1,835,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | NULL | 2023-03-02 19:30:27 | Georgia | Bethsaida Rd | 2022-03-31 | |
| CSF- 293 | OSI 623 | Butner Road and Aldredge Road | Tier 1 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | The intersection is being analyzed for traffic improvements including a roundabout alternative. Additional improvements include curb & gutter, drainage, sidewalks, and streetlights. The proposed project will improve safety and relieve congestion. | NULL | NULL | September, 2026 | September, 2026 | December, 2027 | December, 2027 | Sales Tax | $1,480,000 | $0 | $1,480,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2026 | 2023-03-02 19:33:03 | Georgia | Butner Road | 2022-03-31 | |
| CSF- 294 | NULL | Intersection Improvements | Tier 2 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | NULL | NULL | NULL | NULL | NULL | NULL | Sales Tax | $0 | $0 | $0 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | NULL | 2023-03-02 19:19:03 | Georgia | City of South Fulton | 2022-03-31 | ||
| CSF- 295 | OSI 628 | Old Fairburn Road and Thaxton Road | Tier 1 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | The intersection is being analyzed for traffic improvements including a roundabout alternative. Additional improvements include curb & gutter, drainage, sidewalks, and streetlights. The proposed project will improve safety and relieve congestion. | NULL | NULL | June, 2025 | June, 2025 | June, 2026 | June, 2026 | Sales Tax | $1,480,000 | $0 | $1,480,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2026 | 2023-03-02 19:36:03 | Georgia | Old Fairburn Road | 2022-03-31 | |
| CSF- 296 | OSI 629 | Ono Rd/Hobgood Rd and Rivertown Rd | Tier 1 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | The intersection is being analyzed for traffic improvements including a roundabout alternative. Additional improvements include curb & gutter, drainage, sidewalks, and streetlights. The proposed project will improve safety and relieve congestion. | NULL | NULL | September, 2024 | September, 2024 | December, 2025 | December, 2025 | Sales Tax | $2,238,000 | $0 | $2,238,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2024 | 2023-03-02 19:38:55 | Georgia | Ono Rd/Hobgood Rd | 2022-03-31 | |
| CSF- 297 | OSI 801 | Cascade Road (New Hope to City of Atlanta) | Tier 1 | Operation and Safety Improvements | TSPLOST2 | City of South Fulton | Planning | Connected vehicles deployment phase 2: connected vehicle signal communication upgrades, including all signals on all roads, excluding those already upgraded or programmed for upgrade through CV1K initiative or through connected vehicles deployment phase 1 | NULL | NULL | October, 2026 | October, 2026 | June, 2027 | June, 2027 | Sales Tax | $2,450,000 | $0 | $2,450,000 | NULL | NULL | Active | jeff.mueller@cityofsouthfultonga.gov | 2027 | 2023-03-02 19:53:54 | Georgia | Cascade Road | 2022-03-31 | |
| SUM = 193,906,703 | SUM = 142,040,425,058 | SUM = -141,846,518,355 |