<?xml version="1.0" standalone="yes"?>
<Table name="TSPLOSTProjects">
    <Row>
        <ProjectID>CSF- 51</ProjectID>
        <LocalID>B 500</LocalID>
        <ProjectNameTitle>Butner Road over Camp Creek</ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Bridges</ProjectType>
        <InitiatveType>TSPLOST</InitiatveType>
        <City>City of South Fulton</City>
        <CurrentStage>Design</CurrentStage>
        <ProjectDescription>The proposed Butner Road over Camp Creek includes improvements to the bridge that will extend to the Camp Creek Parkway edge of pavement on the south leg of the intersection.  A new bridge is proposed to replace the existing near the Butner Road/Camp Creek Parkway intersection. The proposed bridge will be wide enough to accommodate two traffic lanes of 24-ft wide, 30'' curb and gutter and 12-ft wide pedestrian sidewalk on the west side to tie into a proposed multi-use trail off the bridge and 6-ft wide sidewalk on the east side.  A turning lane will be designed off the bridge to finish free flow and stacking length up to the intersection with Camp Creek Parkway. </ProjectDescription>
        <ConstructionFirmSelected></ConstructionFirmSelected>
        <DesignFirmSelected>William-Russell & Johnson</DesignFirmSelected>
        <EstimatedDesignCompletionDate>December, 2022</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>April, 2020</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>September, 2024</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate></EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite></LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$1,600,000</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$61,911</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$1,538,089</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Active</Status>
        <Editor>roussan.francois@fultoncountyga.gov</Editor>
        <ProjectYear>2019</ProjectYear>
        <LastUpdate>2023-03-05 00:19:21</LastUpdate>
        <State></State>
        <Address></Address>
        <CreationDate></CreationDate>
    </Row>
</Table>