        <ProjectID>JCR- 2</ProjectID>
        <LocalID>JCR-001</LocalID>
        <ProjectNameTitle>Medlock Bridge Capacity Project (Chattahoochee River to McGinnis Ferry) </ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Congestion Relief</ProjectType>
        <InitiatveType>TSPLOST</InitiatveType>
        <City>Johns Creek</City>
        <CurrentStage>Land</CurrentStage>
        <ProjectDescription>This project will improve intersections along the Medlock Bridge Road corridor and improve or add pedestrian facilities. 
</ProjectDescription>
        <ConstructionFirmSelected></ConstructionFirmSelected>
        <DesignFirmSelected></DesignFirmSelected>
        <EstimatedDesignCompletionDate></EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject></EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate></EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate></EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite>https://www.johnscreekga.gov/Residents/Public-Works/TSPLOST/Medlock-Bridge-Road-Capacity-Project</LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$2,500,000</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$42,336</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$2,457,664</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Gray</ScheduleStatus>
        <Status>Active</Status>
        <Editor>kevin.albi@johnscreekga.gov</Editor>
        <ProjectYear></ProjectYear>
        <LastUpdate>2024-07-11 11:56:44</LastUpdate>
        <State>Georgia</State>
        <Address>City of Johns Creek</Address>
        <CreationDate>2024-07-11</CreationDate>
    </Row>
</Table>