<?xml version="1.0" standalone="yes"?>
<Table name="TSPLOSTProjects">
    <Row>
        <ProjectID>MIL- 11</ProjectID>
        <LocalID>MIL-009</LocalID>
        <ProjectNameTitle>SR 140 at Green Road Intersection Improvements </ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Operation and Safety Improvements</ProjectType>
        <InitiatveType>TSPLOST</InitiatveType>
        <City>Milton</City>
        <CurrentStage>Land</CurrentStage>
        <ProjectDescription>Operation improvements at the intersection that may include a traffic signal and interconnection to other signals on the SR 140 corridor</ProjectDescription>
        <ConstructionFirmSelected></ConstructionFirmSelected>
        <DesignFirmSelected>Practical Design Partners</DesignFirmSelected>
        <EstimatedDesignCompletionDate>January, 2027</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>April, 2021</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>July, 2028</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>July, 2028</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite>https://cleargov.com/georgia/fulton/city/milton/projects/1213/sr-140-(arnold-mill-road)-at-green-road-_-tsplost</LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$1,060,000</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$63,400</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$996,600</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Active</Status>
        <Editor>kathy.stallard@miltonga.gov</Editor>
        <ProjectYear></ProjectYear>
        <LastUpdate>2026-02-27 09:03:47</LastUpdate>
        <State></State>
        <Address></Address>
        <CreationDate></CreationDate>
    </Row>
</Table>