        <ProjectID>CSS- 28</ProjectID>
        <LocalID>TS168</LocalID>
        <ProjectNameTitle>Dalrymple Road - existing sidewalk at Princeton Sq (@Princeton Way) to Duncourtney Dr.</ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Pedestrian and Bike Improvements</ProjectType>
        <InitiatveType>TSPLOST</InitiatveType>
        <City>Sandy Springs</City>
        <CurrentStage>Completed</CurrentStage>
        <ProjectDescription>Connect the sidewalk system on north side of Dalrymple Road from Princeton Way to Duncourtney Dr.  May need mid-block crossing at Duncourtney Dr to the existing sidewalk on south side</ProjectDescription>
        <ConstructionFirmSelected>Construction 57</ConstructionFirmSelected>
        <DesignFirmSelected>KCI</DesignFirmSelected>
        <EstimatedDesignCompletionDate>September, 2021</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>February, 2020</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>April, 2023</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>March, 2023</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite></LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$759,155</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$426,265</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$332,890</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Active</Status>
        <Editor>ajohnson@sandyspringsga.gov</Editor>
        <ProjectYear>2023</ProjectYear>
        <LastUpdate>2023-04-27 13:47:17</LastUpdate>