<?xml version="1.0" standalone="yes"?>
<Table name="TSPLOSTProjects">
    <Row>
        <ProjectID>FA- 46</ProjectID>
        <LocalID>26-004</LocalID>
        <ProjectNameTitle>Roadway Improvements on Various City Roads</ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Maintenance and Safety Enhancements</ProjectType>
        <InitiatveType>TSPLOST2</InitiatveType>
        <City>Fairburn</City>
        <CurrentStage>Construction</CurrentStage>
        <ProjectDescription>The Project was put out to bid April 22, 2026. The Bid Opening date was May 22, 2026
The Contract Award to Shepco Paving, Inc. for the Roadway Improvements on Various City Roads Project for the bid amount of $2,008,660.20 was approved by Mayor & Council at the June 8, 2026, City Council Meeting. The Notice of Award was issued to Shepco Paving, Inc. on June 10th, 2026. The Notice to Proceed (NTP) with Construction Date was July 13th, 2026.  
In this year's City-Wide Resurfacing Project approximately ten (10) centerline miles of roadway, which includes eight (8) residential subdivisions will be resurfaced.  
The City of Fairburn will combine Grant Funding and TSPLOST Funding to deliver this project to take advantage of the economies of scale. In doing so, the first $253,421.47 in project expenditures will be covered by an LMIG Grant from the Georgia Department of Transportation (GDOT); and the second $276,464.46 in project expenditures will be covered by a Local Road Assistance Grant from GDOT, for a total of $529,885.93 collectively to be covered by grants. The remaining project expenditures ($1,478,774.27) will be covered by TSPLOST Funds. 
</ProjectDescription>
        <ConstructionFirmSelected>Shepco Paving, Inc</ConstructionFirmSelected>
        <DesignFirmSelected>In-House</DesignFirmSelected>
        <EstimatedDesignCompletionDate>March, 2026</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>July, 2026</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>July, 2026</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>December, 2026</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite>Fairburn</LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$2,008,660</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$0</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$2,008,660</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Active</Status>
        <Editor>lthompson@fairburn.com</Editor>
        <ProjectYear>2026</ProjectYear>
        <LastUpdate>2026-09-02 12:58:12</LastUpdate>
        <State>GA</State>
        <Address>City of Fairburn</Address>
        <CreationDate>2022-03-31</CreationDate>
    </Row>
</Table>