        <ProjectID>FA- 41</ProjectID>
        <LocalID>24-009</LocalID>
        <ProjectNameTitle>Cleckler Rd Full-Depth Reclamation Project</ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Maintenance and Safety Enhancements</ProjectType>
        <InitiatveType>TSPLOST2</InitiatveType>
        <City>Fairburn</City>
        <CurrentStage>Bidding</CurrentStage>
        <ProjectDescription>Full-Depth Reclamation of Cleckler Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers  (RPMs), and manhole and water valve adjustments.  
</ProjectDescription>
        <ConstructionFirmSelected>BLOUNT CONSTRUCTION</ConstructionFirmSelected>
        <DesignFirmSelected>SOUTHEASTERN ENGINEERING INC.</DesignFirmSelected>
        <EstimatedDesignCompletionDate>May, 2024</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>July, 2024</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>November, 2024</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>October, 2024</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite></LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$209,041</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$0</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$209,041</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Active</Status>
        <Editor>anthony.belcher@fairburn.com</Editor>
        <ProjectYear>2024</ProjectYear>
        <LastUpdate>2025-08-04 16:18:35</LastUpdate>
        <State>GA</State>
        <Address>Cleckler Rd.</Address>
        <CreationDate>2025-05-06</CreationDate>
    </Row>
</Table>