        <ProjectID>FA- 40</ProjectID>
        <LocalID>25-003</LocalID>
        <ProjectNameTitle>MULLIS STREET PEDESTRIAN IMPROVEMENTS PROJECT </ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Pedestrian and Bike Improvements</ProjectType>
        <InitiatveType>TSPLOST2</InitiatveType>
        <City>Fairburn</City>
        <CurrentStage>Construction</CurrentStage>
        <ProjectDescription>The installation of a 5-foot concrete sidewalk with a 2-foot beauty strip along Mullis Street, from West Campbellton Street to Dodd Street, and from Dodd Street to Strickland Street. The project also entails the installation of pedestrian improvements on a section of Dodd Street, from Mullis Street to W. Broad Street. The work includes the removal of existing curb & gutter and header curb, and the installation of new header curb and sidewalk. This contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt as well as clean up and backfilling. The scope of Add Alternate #1 consists of the installation of pedestrian lighting</ProjectDescription>
        <ConstructionFirmSelected>CONSTRUCTION 57 INC.</ConstructionFirmSelected>
        <DesignFirmSelected>POND ENGINEERING</DesignFirmSelected>
        <EstimatedDesignCompletionDate>March, 2025</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>May, 2025</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>July, 2025</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>June, 2025</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite></LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$570,201</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$570,201</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$0</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Active</Status>
        <Editor>anthony.belcher@fairburn.com</Editor>
        <ProjectYear>2025</ProjectYear>
        <LastUpdate>2025-05-06 10:21:42</LastUpdate>