        <ProjectID>JCR- 53</ProjectID>
        <LocalID>TS0250</LocalID>
        <ProjectNameTitle>Town Center - Pedestrian Crossing</ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Pedestrian and Bike Improvements</ProjectType>
        <InitiatveType>TSPLOST2</InitiatveType>
        <City>Johns Creek</City>
        <CurrentStage>Completed</CurrentStage>
        <ProjectDescription>Pedestrian crossing on SR 141/ Medlock Bridge Road in the Town Center redevelopment area.</ProjectDescription>
        <ConstructionFirmSelected>Vertical Earth</ConstructionFirmSelected>
        <DesignFirmSelected>Michael Baker</DesignFirmSelected>
        <EstimatedDesignCompletionDate>September, 2024</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>November, 2024</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>July, 2026</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>July, 2026</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite></LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$6,000,000</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$7,913,355</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$-1,913,355</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Red</CostStatus>
        <ScheduleStatus>Yellow</ScheduleStatus>
        <Status>Inactive</Status>
        <Editor>brian.oconnor@johnscreekga.gov</Editor>
        <ProjectYear></ProjectYear>
        <LastUpdate>2026-08-17 16:53:47</LastUpdate>
        <State>Georgia </State>
        <Address>City of Johns Creek</Address>
        <CreationDate>2022-03-31</CreationDate>