        <ProjectID>JCR- 47</ProjectID>
        <LocalID>TS0250</LocalID>
        <ProjectNameTitle>Town Center - Creekside North Pond Trail</ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Pedestrian and Bike Improvements</ProjectType>
        <InitiatveType>TSPLOST2</InitiatveType>
        <City>Johns Creek</City>
        <CurrentStage>Completed</CurrentStage>
        <ProjectDescription>Pedestrian Trail connectivity within Town Center redevelopment area.</ProjectDescription>
        <ConstructionFirmSelected>Reeves Young</ConstructionFirmSelected>
        <DesignFirmSelected>Foresite</DesignFirmSelected>
        <EstimatedDesignCompletionDate>December, 2023</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>February, 2024</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>March, 2026</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>March, 2026</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite></LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$2,000,000</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$1,941,926</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$58,074</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Inactive</Status>
        <Editor>brian.oconnor@johnscreekga.gov</Editor>
        <ProjectYear></ProjectYear>
        <LastUpdate>2026-08-17 16:39:27</LastUpdate>
        <State>Georgia </State>
        <Address>City of Johns Creek</Address>
        <CreationDate>2022-03-31</CreationDate>