        <ProjectID>EP- 5</ProjectID>
        <LocalID>EP-177</LocalID>
        <ProjectNameTitle>Washington Road Sidewalk </ProjectNameTitle>
        <Tier>Tier 1</Tier>
        <ProjectType>Pedestrian Improvements</ProjectType>
        <InitiatveType>TSPLOST</InitiatveType>
        <City>East Point</City>
        <CurrentStage>Construction</CurrentStage>
        <ProjectDescription>The Project was bid Out for Construction.   The lowest apparent bidder was DAF Concrete. Project is for new installation of sidewalk along the Washington Road corridor from I-285 to Delowe Drive.</ProjectDescription>
        <ConstructionFirmSelected>DAF Concrete, LLC</ConstructionFirmSelected>
        <DesignFirmSelected>Moreland Altobelli (ATLAS)</DesignFirmSelected>
        <EstimatedDesignCompletionDate>June, 2018</EstimatedDesignCompletionDate>
        <EstimatedStartDateForProject>June, 2021</EstimatedStartDateForProject>
        <EstimatedConstructionCompletionDate>June, 2022</EstimatedConstructionCompletionDate>
        <EstimatedSubstantialCompletionDate>June, 2022</EstimatedSubstantialCompletionDate>
        <LinkToExternalWebsite>http://www.eastpointcity.org</LinkToExternalWebsite>
        <PrimaryFundingSource>Sales Tax</PrimaryFundingSource>
        <TSPLOSTBudget($)>$1,993,420</TSPLOSTBudget($)>
        <TSPLOSTDollarsSpent($)>$322,000</TSPLOSTDollarsSpent($)>
        <TSPLOSTDollarsCommitted(notspent)($)>$1,671,420</TSPLOSTDollarsCommitted(notspent)($)>
        <CostStatus>Green</CostStatus>
        <ScheduleStatus>Green</ScheduleStatus>
        <Status>Active</Status>
        <Editor>Cadell Hall</Editor>
        <ProjectYear>2021</ProjectYear>
        <LastUpdate>2021-10-11 22:09:50</LastUpdate>